INDUSTRIAL CASE|MECHANICAL ENGINEERING|COMPRESSOR EQUIPMENT

IE A098ACT OF JSC UKRELEKTROMASH DATED 18.01.2001

Compressor 2VM 4-24/9 M-1: time to build 8 atm fell from 1 min 36 s to 1 min 00 s

Time to reach working pressure decreased, compressor output increased and held under load. 60 % — compressor output, build-up to 8 atm: 1 min 36 s → 1 min 00 s (2001).

JSC Ukrelektromash, Kharkiv Electrical Engineering Plant  ·  boiler and compressor section  ·  approved by the plant's technical director F. F. Laptsevich

Kharkiv, Ukraine  ·  contract No. 91-P dated 01.12.2000 · measurements on 08.12.2000 and 18.01.2001

PRODUCTXADO compoundrestorative repair by XADO technology® · contract No. 91-P dated 01.12.2000
TEST OBJECTPiston compressor
2VM 4-24/9 M-1
compressor No. 8 of the boiler and compressor section · 3 m³ receiver, working pressure 8 atm
DOCUMENT TYPETechnical act,
signed by both parties
seal and the technical director's “Approved” endorsement

Key result

↑60%
compressor output, build-up to 8 atm:1 min 36 s → 1 min 00 s
EQUIPMENTOPERATING CONDITIONSWHAT WAS MEASURED
Piston compressor 2VM 4-24/9 M-1, No. 8Boiler and compressor section of the plant, 3 m³ receiver, working pressure 8 atmTime to build working pressure from 0 to 8 atm

Measurements before and after the restorative repair

PARAMETERBEFORE REPAIR, 08.12.2000AFTER, 400 h OF OPERATION
Time to build working pressure from 0 to 8 atm1 min 36 s1 min 00 s
Compressor output by filling of the 3 m³ receiver100 %160 %

Output was determined from the time to fill the 3 m³ receiver to 8 atm; the standard instruments and sensors of the compressor unit were used for the measurements.

Conclusion of the plant commission

The commission of JSC Ukrelektromash — the deputy chief engineer, the head of the maintenance and repair shop, and the foreman of the boiler and compressor section — recorded: after the restorative repair of the compressor 2VM 4-24/9 M-1 by XADO technology® using the XADO compound, the time to build working pressure in the 3 m³ receiver fell from 1 min 36 s to 1 min 00 s. The “after” measurement was taken at 400 hours of operation. The act's conclusion verbatim: “The results obtained indicate the expediency of carrying out restorative repair by XADO technology® on all industrial equipment” of the plant. The act was approved by the plant's technical director under seal.

Current equivalent

Revitalizant gel for compressors and bearings →

Piston, screw and centrifugal compressors; rolling and sliding bearings running in an oil bath; machine-tool spindle units and slideways.

How such units are treated: Compressor

Limits of this report: The results relate to the piston compressor 2VM 4-24/9 M-1 of the boiler and compressor section of JSC Ukrelektromash and to the duty of filling a 3 m³ receiver to 8 atm; on other equipment and in other duties the figures may differ.

Request a pilot for this unit

XADO Pilot Testing Programme

Application submitted by

Pilot treatment on the enterprise's equipment

  • any oil- or grease-lubricated assemblies: gearboxes, engines, compressors, bearings and others;
  • treatment within the regular operating cycle, without halting production;
  • instrumental measurements before and after: vibration, temperature, power consumption or current;
  • procedure for the specific assembly, dose calculation and support from a XADO engineer.

After the application, a XADO engineer will agree the units and the list of measurements with you.