IE A045ZMIIVSKA TPP TEST REPORT · TURBINE SHOP
NTS-7G district heating pump: lower current draw and bearing vibration, no teardown
The motor drew less current, bearing housings quietened down, the pump kept running without teardown. NTS-7G district heating pump, Zmiivska TPP, turbine shop.
signatures, seal
Key results
| MACHINE | CONDITION AT START OF TESTING | WHAT WAS MEASURED |
|---|---|---|
| NTS-7G district heating pump | In service; bearings No. 3086313 and No. 6313, radial clearance 0.19 and 0.08 mm | Vibration of the front and rear bearing housings — vertical and horizontal |
| Pump drive motor | In service; bearings No. 322 and No. 2322, radial clearance 0.18 and 0.13 mm | Current draw of phases A, B, C; vibration of the front bearing housing |
Motor current draw
| MODE | BEFORE TREATMENT | AFTER 515 H | CHANGE |
|---|---|---|---|
| Under load — operating mode | 25.8 A | 22.8 A | −11.6 % |
| No load | 20.4 A | 16.8 A | −17.6 % |
Current is identical across all three phases A, B, C. Under load: pump inlet pressure 2.4 kgf/cm², outlet pressure 8 kgf/cm².
Vibration of the pump and motor bearing housings
| MEASUREMENT POINT | VIBRATION ACCELERATION, m/s² | VIBRATION VELOCITY, mm/s | VIBRATION DISPLACEMENT, µm |
|---|---|---|---|
| Pump, front housing, vertical | 12.9 → 18.3 | 1.46 → 0.904 | 18.9 → 9.97 |
| Pump, front housing, horizontal | 13.0 → 10.0 | 0.893 → 0.518 | 9.95 → 4.53 |
| Pump, rear housing, vertical | 27.0 → 17.3 | 1.00 → 0.763 | 15.0 → 13.2 |
| Pump, rear housing, horizontal | 13.9 → 9.05 | 0.865 → 0.539 | 8.03 → 6.45 |
| Motor, front housing, vertical | 224.0 → 47.9 | 0.931 → 0.804 | 12.7 → 12.4 |
| Motor, front housing, horizontal | 166.0 → 56.9 | 1.30 → 1.48 | 21.5 → 22.6 |
Six control points on the bearing housings; for each of the three parameters vibration decreased at five points out of six.
Findings of the Zmiivska TPP commission
The results relate to the NTS-7G district heating pump with its drive motor at Zmiivska TPP; on other equipment and in other operating modes the figures may differ. The economic calculation is given in the report itself, at the plant tariff of 0.14 UAH per 1 kW·h for 2005. The original report with signatures and seal is published in full and available for download.
Current equivalent
- Revitalizant gel for compressors and bearingsCompressors · bearings · spindles
- Revitalizant gel for hydraulic systemsHydraulics · pumps · hydraulic motors
How such units are treated: