K-500 turbocompressors: less power draw and vibration without opening the unit

Energy consumption dropped at the same load, stator current fell, support vibration decreased. 2.7–3.8 % — power consumption under load, 2334–2998 → 2248–2918 kW; 2.2–3.8 % — stator current of the drive electric motor, 193–266 → 188–256 A; 19–56 % — vibration displacement of bearing supports No. 1-9, all three units (2005–2007).

JSC Zaporizhzhia Iron Ore Plant, power shop — air-blower station  ·  reports approved by the plant’s chief power engineer Yu. N. Bezruchko

Ukraine  ·  reports dated 25.10.2005, April 2006 and 22.03.2007

PRODUCTXADO revitalizantsstaged addition of the calculated amount of the compound into the oil bath of the running unit
TEST OBJECTK-500 turbocompressor unitsserial No. 86, No. 2724, No. 11371 · line “turbocompressor — gearbox — electric motor”
DOCUMENT TYPEThree plant reports
with signatures and stamps

What repeated on all three units

↓2.7–3.8%
power consumption under load,2334–2998 → 2248–2918 kW
↓2.2–3.8%
stator current of the drive electric motor,193–266 → 188–256 A
↓19–56%
vibration displacement of bearing supports No. 1-9, all three units
MACHINEOPERATING TIME BEFORE CONTROL MEASUREMENTREPORT DATEWHAT WAS MEASURED
Machine No. 1, serial No. 86817 h25.10.2005power, current, vibration at 18 points, oil condition
Machine No. 2, serial No. 2724422 hApril 2006power, current, vibration at 16 points
Machine No. 3, serial No. 11371655 h22.03.2007power, current, vibration at 16 points, oil temperature

Power consumption by unit

MACHINEMODEBEFORE, kWAFTER, kWCHANGE
Machine No. 1, serial No. 86under load23342248−3.7 %
Machine No. 1, serial No. 86idle586547−6.7 %
Machine No. 2, serial No. 2724under load25762477−3.8 %
Machine No. 2, serial No. 2724idle723662−8.4 %
Machine No. 3, serial No. 11371under load29982918−2.7 %
Machine No. 3, serial No. 11371idle11221036−7.7 %

Power was recorded by the unit’s standard control system. The report conclusions state a reduction of 2.7–3.8 % under load and 6.7–8.4 % at idle.

Stator current of the drive electric motor, under-load mode

MACHINEBEFORE, AAFTER, ACHANGE
Machine No. 1, serial No. 86193188−2.6 %
Machine No. 2, serial No. 2724230225−2.2 %
Machine No. 3, serial No. 11371266256−3.8 %

Current was taken by the same standard system and in the same mode as power — an independent confirmation of the result on the electrical side.

Vibration of the bearing supports

MACHINEMEASURING POINTSTYPICAL REDUCTIONMAXIMUM
Machine No. 1, serial No. 861814–61 %82 %
Machine No. 2, serial No. 27241622–41 %62 %
Machine No. 3, serial No. 113711618–56 %85 %

SENDIG 911 vibrometer, vibration displacement of supports No. 1-9 — turbocompressor, gearbox and electric motor. Of the 50 points on the three units, 49 showed a reduction.

Conclusions of the plant reports

Three reports, approved by the chief power engineer of JSC Zaporizhzhia Iron Ore Plant, state one and the same result. For machine No. 2, serial No. 2724, the treatment “made it possible to reduce the power consumption under load by 3.8%, while at idle the reduction in power consumption was 8.4%. In addition, the vibration parameters decreased at all bearing supports by 22–57%”. For machine No. 3, serial No. 11371 — 2.7% under load and 8.4% at idle, “at individual points a reduction of 35–57%”; for machine No. 1, serial No. 86 — 3.2% and 6.7%. The reports attribute the drop in vibration to the establishment of optimal thermal clearances in the bearings, which allows their service life to be extended. Not a single unit was disassembled for this: the compound was added in stages into the oil bath of the running machine.

Current equivalent

How such units are treated: BearingsReduction gearbox

About this result: VibrationPower consumption

Limits of this report: The results relate to the K-500 turbocompressor units of the air-blower station of JSC Zaporizhzhia Iron Ore Plant and to the operating modes recorded in the reports; on other machines and in other modes the figures may differ. The measurements were carried out by the personnel of the plant’s power shop using the standard monitoring system together with representatives of XADO LLC.

Request a pilot for this unit

XADO Pilot Testing Programme

Application submitted by

Pilot treatment on the enterprise's equipment

  • any oil- or grease-lubricated assemblies: gearboxes, engines, compressors, bearings and others;
  • treatment within the regular operating cycle, without halting production;
  • instrumental measurements before and after: vibration, temperature, power consumption or current;
  • procedure for the specific assembly, dose calculation and support from a XADO engineer.

After the application, a XADO engineer will agree the units and the list of measurements with you.